Case study ‐ Queensland Health 
Payroll 
Source: Auditor General Report to 
Parliament No. 7 for 2010, (June) 
Notes prepared by Harold Ainsworth 
1
Background
• Qld Health used LATTICE Payroll & ESP Rostering 
system in place since 1997
• System had to be replaced by July 2008 as no longer 
supported by supplier
• CorpTech undertaking the implementation of whole 
of Gov’t SAP HR system from 2002 
• Queensland Health due to receive the new whole of 
Government SAP HR system by 2006 ‐ but it was 
delayed
2
Roles 
Party 
Role 
Corp Tech 
Shared services IT provider for Queensland Government managed 
by Dept. of Public Works
Manage the prime contract
IBM
Prime contractor for SAP HR & Workbrain rostering to replace 
LATTICE
Qld Health
Business user of SAP HR
Payroll requirements
Data cleansing and migration
User acceptance
Staff training
Business processes
3
Key dates 
Implement first version of SAP HR Dept Housing 
March 07 
Review of Shared Services implementation found problems with program 
implementation and recommended appointment of prime contractor 
Aug 07
Queensland Health and CorpTech decide to implement new payroll system 
due to risk with LATTICE
Late 07
IBM awarded Prime Contract for rest Qld Gov’t SAP HR implementation 
Nov 07 
Planning & scoping LATTICE replacement system 
Nov 07 –
Jan 08 
IBM proposal for full LATTICE system replacement across whole of Gov’t 
June 08 
Extension of support negotiated with LATTICE Supplier 
Sept 08 
IBM finds their costs of SAP HR underestimated – role now limited to Qld 
Health payroll 
Oct  08 
New structure Qld Health Implementation of Continuity Project Board 
established  ( QHIC Project Board)  
June 09 
Go live 
March 10 
4
Governance 1 
Approved June 08
Originally covered 
whole of Gov’t 
implementation 
5
Governance 2 
Governance 
re‐focussed 
on Qld 
Health 
6
Requirements 
•
Complex requirements: 
–
–
–
–
13 awards
200 allowances
24,000 different combinations
78,000 employees
Old system LATTICE due to limited capability required up to 20% of payees 
pay to be re‐worked
• Complex to integrate SAP system with Health Finance
• Decided to utilise Housing system as basis for Health – despite Housing 
system applying to small number of staff who worked in standard office 
environment 
• Qld Health not involved in sign‐off of key deliverables 
• Sept 09 ‐ 20 months after start Qld Health formally approved scope 
• During testing many defects found and it was argued they were changes in 
requirements   
•
7
Key events 
• IBM delivered estimate of $6.13 mill to replace LATTICE 
for Qld Health  ‐ based on “like for like” with Housing 
system 
• Then at cost of $0.926 mill developed more detailed plan 
for LATTICE, and made no change to implementation 
estimate
• Did not meet Nov 08 implementation date – reset for 
May 09 
• June, August & Nov 09 dates also missed. 
• March 10 cost estimate for IBM was $24 mill for Qld 
Health HR system 
8
Implementation issues 
• Parallel testing conducted same time as user acceptance testing
• Project Board changed classification of defects, allowing some 
defects to be downgraded, and allowing test exit criteria to be 
achieved  
• Full parallel run not conducted due to complexity & size of this task 
• Independent company who conducted User acceptance test for Qld 
Health  said “too many defects to go live” also testing inefficient 
due to fixing errors and testing in parallel
• Project Board decided to proceed anyway. Risks at implementation 
not sufficiently quantified, especially if they materialised .      
• Exception report not provided to operations staff. Also they were 
not familiar with new procedures.  
• Strict rules applied by new system – eg no roster no pay – which 
caused backlog of processing 
9
Post‐implementation issues 
Rostering  System performance issues – slow processing 
Overnight batch processing taking longer than expected 
Backlog of work due to initial problems 
New processes introduced including separation of roles 
for payroll and rostering – reduced turnaround time 
when problems occurred 
• Incorrect data in system – various reasons 
• Lack of clear end to end process for resolving both 
business and technical issues
•
•
•
•
10
Costs
IBM initial Payroll system costs  estimate (+ Qld Health & CorpTech) 
$6.19 mill
IBM cost on Qld Health Payroll (after 47 changes due to unclear scope)  $ 21 mill
Total direct costs at March 10 – CorpTech, Qld Health and IBM 
$ 65 mill
IBM payments on whole of Government system solutions 
(involves some SAP technical libraries for future finance and HR 
systems implementation – not yet used)
$37.5 mill
Total cost ‐ at end March 10 for SAP HR 
$ 102  Mill 
To provide context ‐ funding was approved of $153 mill for SAP HR & completion 
current Finance systems across 4 agencies in Nov 07 
11
Observations
• Shared services arrangements:
– CorpTech signed with Supplier but no record of agreement from 
User  (Qld Health)
– System owner? Process owner? Lack of clarity about roles 
• A specific PM method not applied
• Having IBM as overall Project Manager could lead to 
conflict of interest and compromises 
• Gating or end‐stage review required on large scale high‐
risk projects
• Documented learnings from Housing HR implementation 
also repeated in Health implementation – so no learning!     
12
Conclusions
Roles and responsibilities for Governance not clear
Inadequate documentation of requirements
Implementation period increased from 8 ‐ 26 months
Business needs review did not occur
Implementation risks not identified and planned for
Usability testing in the business environment not 
performed – especially check out of processes
• No Business Continuity Plan in place
• Key performance reports used by CorpTech not available 
at initial Payroll processing
• Several other changes to payroll admin practices 
implemented at the same time
•
•
•
•
•
•
13
Key recommendations
Simplify award structures first
Clear accountabilities for Governance
Assess impact of business change
Go‐live decision to include business readiness
Have fall‐back plans in place
Contracts with third parties need to have tight 
controls over scope of work
• Planning assumptions to be rigorously challenged  
•
•
•
•
•
•
14
Outcomes 
• Adverse publicity in press about the payroll problems
• IBM lost a subsequent contract with another 
Government agency (late 2010)
• KPMG called in to “clean‐up”
• Government investigation showed that payroll now 
requires 1,000 additional staff to make it work  
• Additional Government investigation under way  
15
Other resources 
• YouTube videos 
• Queensland Health Payroll System Commission of 
Inquiry, Report 31 July 2013, by The Honourable 
Richard N Chesterman AO RFD QC (read the 
Summary at end) 
16
…
Purchase answer to see full
attachment

Academic integrity note

Use this educational resource to build your understanding. Follow your institution’s rules and cite sources appropriately.

Want feedback on your own work?

Request Academic Support

Leave a Reply

Your email address will not be published. Required fields are marked *