From this data,
calculate the project’s ETC. Activity A is 60% complete at a cost so far of
$100,000. It was estimated to cost $200,000 when finished. It is at the end of
week three of five. Activity B is 85% complete at a cost so far of $50,000. It
was estimated to cost $80,000 when finished. It is at the end of week four of
five. Activity C is complete at a cost so far of $110,000. It was estimated to
cost $100,000 dollars when finished