Work Breakdown Structure Essential Components
For this assignment, you will develop a WBS.
· There is no template provided this week for your WBS. Please submit your WBS in MS Word, MS Excel, MS Project, or pdf format.
· At a minimum, your WBS should:
– Identify ALL work related to your project (your WBS should comply with the 100% rule)
– Contain at least three levels, NOT including the overall project level. So at a minimum, your WBS should look like this:
§ OVERALL PROJECT NAME
· 1.0 WBS level 1
o 1.1 WBS level 2
§ 1.1.1 WBS level 3
– Contain at least 30-40 lines of detail
– Include a code of accounts (numbering scheme) for each WBS line item
– Be deliverables-oriented, meaning it should NOT contain any activities (all WBS items should be nouns, no verbs should be used. See this weeks course materials for clarity about this.)
– Use the adjective / noun format for all deliverables (also see this weeks course materials about this.)